January 2020 Progress Report

Building for the new ISG campus is well underway. 

The bulk excavation work for both schools has been completed, and the piling work with 1,011 piles that began in mid-August was completed in early December ahead of schedule. Excavation for the swimming pool and sports area has also been completed.

The main activities currently on site in both schools is the construction of the pile cap and grade beams, which will be followed by the casting of the concrete columns to raise the building structure. In the American school, the first floor slab has been poured in one area which is in line with the project schedule. In the British school the basement work, which is the main challenge in terms of the structural work for this building, is making good progress.

We are very pleased to announce that construction is on schedule and progressing well.